1.Initial Inspection
2.Buffing
3.Buzz Out
4.Cementing
5. Building
6. Curing
7. Final Inspection
Usmeta
1.Initial Inspection
To determine or inspect the condition of the
casings weather can be retread or not.
2.Buffing
To remove all the remaining unwanted old
tread from casing and prepare suitable surface
which the new tread is to be bonded.
Minor Repair
Major Repair
3.Buzz
Out
To remove the small plies appear on the
surface of buff tyre and remove small stones
or nail trapped in the casing tyre or patch
the tyre if the tyre have small hole.
4.Cementing
To apply adhesion to the buff surface.
5.
Building (Building Precured)
The process that attach the liner or camelback
to the buff casing.
5.
Building (Building Hotcured)
6.
Curing (Hotcured)
The process that cured the rubber (cushion
gum or camelback) at certain time, temperature
and pressure.
6.
Curing (Hotcured - EM)
6.
Curing (Precured)
7.
Final Inspection
To inspect the tyre after curing process
weather the tyre have any defect or not
before sent to finished
good storage.